| Bid Package | Scope | RFQ | | | RFP | | |
| | | Start | Finish | Duration (wks) | Start | Finish | Pre-Bid Conference |
| 7 | Below Grade Waterproofing |
FINISHED | FINISHED | 3 | FINISHED | FINISHED | 10/20/10 |
| 14.0 | Structural Concrete & Interior Nosings- By DPW |
FINISHED | FINISHED | | FINISHED | FINISHED | 08/27/10 |
| 15.1 | Public Elevator Cab Interiors |
FINISHED | FINISHED | 3 | TBD | TBD | TBD |
| 17 | Miscellaneous Iron, Metal Stairs & Railings, Wire Rope, Sunshade Devices |
FINISHED | FINISHED | 3 | 04/14/11 | 05/11/11 | 04/21/11 |
| 18 | Window Washing System - By DPW |
| | N/A | | | |
| 19 | Above Grade Waterproofing, Roofing, Flashing, Sheetmetal, Metal Roofing and Metal Canopy |
FINISHED | FINISHED | 3 | 06/07/11 | 06/29/11 | 06/14/11 |
| 20 | Seismic Control |
FINISHED | FINISHED | | 04/14/11 | 05/11/11 | 04/21/11 |
| 21 | NOT USED |
| | | | | |
| 22 | NOT USED |
| | | | | |
| 23 | Casework, Solid Surface Fabrications, Solid Polymer Fabrications |
FINISHED | FINISHED | 3 | 06/07/11 | 06/29/11 | 06/14/11 |
| 24 | Openings |
FINISHED | FINISHED | 3 | 05/10/11 | 06/01/11 | 05/17/11 |
| 25 | NOT USED |
| | | | | |
| 26 | Tile |
FINISHED | FINISHED | 3 | TBD | TBD | |
| 27 | Epoxy Terrazzo |
FINISHED | FINISHED | 3 | 05/10/11 | 06/01/11 | 05/17/11 |
| 28 | Acoustical Ceilings |
FINISHED | FINISHED | 3 | 04/14/11 | 05/11/11 | 04/21/11 |
| 29 | Flooring |
FINISHED | FINISHED | 3 | 05/10/11 | 06/01/11 | 05/17/11 |
| 30 | Wood Ceilings |
TBD | TBD | 3 | TBD | TBD | |
| 31 | Painting, Special Coatings & Fluid Applied Flooring |
FINISHED | FINISHED | 3 | 05/10/11 | 06/01/11 | 05/17/11 |
| 32 | NOT USED |
| | | | | |
| 33 | Signage, Interior & Exterior |
FINISHED | FINISHED | 3 | 05/10/11 | 06/01/11 | 05/17/11 |
| 34 | NOT USED |
| | | | | |
| 35 | NOT USED |
| | | | | |
| 36 | Healthcare Equipment |
FINISHED | FINISHED | 3 | 05/10/11 | 06/01/11 | 06/14/11 |
| 37 | Specialties |
FINISHED | FINISHED | 3 | 04/16/11 | 05/11/11 | 04/21/11 |
| 38 | Window Shades |
FINISHED | FINISHED | 3 | 06/07/11 | 06/24/11 | 06/14/11 |
| 39 | NOT USED |
| | | | | |
| 40 | Food Service Equipment |
FINISHED | FINISHED | 3 | 05/10/11 | 06/01/11 | 05/17/11 |
| 41 | Final Clean |
TBD | TBD | 3 | 06/07/11 | 06/29/11 | 06/14/11 |
| 42 | Architectural Concrete, Curbs & Pads |
FINISHED | FINISHED | 3 | 06/07/11 | 06/29/11 | 06/14/11 |
| 43 | Landscape and Irrigation |
FINISHED | FINISHED | 3 | 06/07/11 | 06/29/11 | 06/14/11 |
| 44 | RF Shielding |
FINISHED | FINISHED | 3 | 06/07/11 | 06/29/11 | 06/14/11 |
| 45 | Interior Glazing |
FINISHED | FINISHED | 3 | 04/14/11 | 05/11/11 | 04/21/11 |
| 46 | Protection |
TBD | TBD | 3 | TBD | TBD | TBD |
| 47 | Bridge and Tunnel Tie In |
TBD | TBD | 3 | TBD | TBD | TBD |
| 48 | Reinstatement |
TBD | TBD | 3 | TBD | TBD | TBD |
| 49 | NOT USED |
| | | | | |
| 50.1 | Winterization Vert. |
FINISHED | FINISHED | 3 | 06/07/11 | 06/29/11 | 06/14/11 |
| 50.2 | Winterization Cond. |
TBD | TBD | 3 | 06/07/11 | 06/29/11 | 06/14/11 |
| | Service Building |
FINISHED | FINISHED | | 05/10/11 | 06/01/11 | 05/07/11 |
| 52.01 | Phase II - Fuel Oil |
FINISHED | FINISHED | 3 | FINISHED | FINISHED | FINISHED |
| 52.04 | Phase II - Site Work |
FINISHED | FINISHED | 3 | FINISHED | FINISHED | FINISHED |
| 52.06 | Phase II - Shotcrete |
FINISHED | FINISHED | 3 | FINISHED | FINISHED | FINISHED |
| 52.08 | Phase II - Reinforcing Steel |
FINISHED | FINISHED | 3 | FINISHED | FINISHED | FINISHED |