The 284 bed/14 operating room hospital and trauma center will provide the only Level 1 Trauma Center for residents of San Francisco and northern San Mateo County. The facility will house cardiology/radiology/auxiliary support and plant services at the B2 level. Preoperative/gastroenterology and a clinical laboratory will be contained at the B1 level. Admitting and emergency will occupy the ground floor level. Obstetrics/pediatrics and NICU will be housed on the second floor. ICU/CCU will be located on the third and fourth floors. Medical surgery and forensic will occupy the fifth and sixth floors and acute care for the elderly will occupy the seventh floor. The tunnel at the B1 level will connect to the nuclear medicine center in the existing hospital and the bridge at the second floor will connect to clinical laboratories, the cafeteria and support services.
The 448,000 sf hospital will be a steel moment frame structure on a mat foundation with base isolators. The hospital will have two (2) levels below grade and eight (8) levels above grade including a mechanical penthouse. Ties to the existing hospital will be made by means of a tunnel at the B1 level and a bridge at the 2nd floor.
The project will be built in 4 phases. Phase I consists of site utilities relocation and replacement; Phase II consists of Service Building modifications and equipment additions; Phase III consists of excavations, foundations and structure frame; and Phase IV consists of the new Acute Building Enclosure and build out.
In order to facilitate the IPD, The Board of Supervisors and the Mayor approved Ordinance No. 202-07, allowing Webcor Builders to hire the following Core Trade Contractors during the Pre-Construction Phase of the Project to assist the Executive Architectural and Engineering team in the Integrated Project Delivery approach: